Sat 1 Math Problem

<p>i always always miss these types of problems. can someone please explain how this problem should be done?</p>

<p>If 15 workers can paint 18 houses in 24 days, how many days will 40 workers take to paint 22 houses?</p>

<p>btw, the answer is 11</p>

<p>It takes 15 workers (24/18) = 1.333 days to paint a single house, so a single worker would take (15)(1.333) = 20 days to paint a single house.
One worker would take (22)(20) days to paint 22 houses.
40 workers could do it in (22)(20)/40 = 11 days.</p>